Guide · Businesses · 3 min read · Updated 17 November 2026
How Resin Factory Floors Are Installed: Step by Step
Short answer
A resin factory floor is installed in stages. The contractor surveys and moisture-tests the slab, prepares it by shot blasting or diamond grinding, repairs cracks, holes and joints, then primes the concrete. Body coats, screeds or self-smoothing layers follow, with aggregate added for slip resistance where needed. After curing, line marking is applied and the floor is handed back for use.
Survey and testing
Every good resin floor starts with a survey. The contractor looks at the concrete, notes cracks, failed joints, old coatings and contamination, and asks how the floor will be used. They test the surface strength and check for moisture, because damp slabs can cause resin to blister or lose adhesion.
The survey also covers practical issues: access for equipment, power supply for shot blasting machines, ventilation and how the work fits around production. A clear understanding of traffic, temperatures, cleaning and chemicals decides which system is specified for each area.
The survey is also the right time to agree the boundaries of each system. Production areas, walkways, stores and loading bays may all need different floors. Marking these on a plan avoids confusion during installation and makes sure the right texture and thickness go in the right place.
- Concrete condition and surface strength
- Moisture content of the slab
- Existing coatings and contamination
- Cracks, holes and joint condition
- Access, power, ventilation and programme
Surface preparation
Preparation removes the weak top layer of concrete, called laitance, along with old coatings, dirt and oil. Shot blasting machines fire steel shot at the floor and vacuum it back, leaving a clean, textured surface. Diamond grinders handle edges, small areas and some coatings. Heavy coatings may need scabbling or planing.
Dust is controlled with vacuum extraction. The Control of Substances Hazardous to Health Regulations 2002 apply to both preparation dust and resin products, so contractors must assess and control exposure. The area should be cleared of stock and people not involved in the work.
| Method | What it does | Best for |
|---|---|---|
| Shot blasting | Removes laitance and light coatings, leaves a key | Large open areas |
| Diamond grinding | Smooths and removes coatings | Edges, small areas, smoother profiles |
| Scabbling or planing | Removes thick coatings and high spots | Heavily coated or uneven floors |
| Degreasing | Breaks down oil contamination | Oil-soaked areas before mechanical preparation |
Repairs and detailing
After preparation, defects in the concrete are easier to see. Cracks are opened and filled with resin, holes and spalled areas are patched with resin mortar, and failed joints are cut out and rebuilt. Joints on forklift routes take the most punishment, so they are often repaired with stronger materials or reinforced arrises.
Details are also prepared at this stage. Edges where the new floor meets doors, drains and walls are cut back to give a clean termination. In food areas, coving is formed at wall junctions so there are no sharp corners where dirt collects. Upstands may be formed around machinery bases.
Joint repairs deserve particular care. Joints that move with the slab should be reinstated as movement joints with a flexible sealant, while dead joints can be filled solid. Bridging a live joint with rigid resin usually leads to a crack reappearing in the new floor above it, which spoils the finish and lets water in.
Priming and laying the system
A primer is applied to seal the concrete and give the resin system a strong bond. Where moisture is a concern, a damp-tolerant primer may be specified. The main system follows: coats rolled on for epoxy coatings, poured and spread for self-smoothing systems, or trowelled for polyurethane screeds.
For anti-slip finishes, aggregate is broadcast into the wet resin, then sealed with a topcoat. The size and amount of aggregate set the level of grip. Temperature, humidity and mixing ratios are monitored throughout, because resin that is mixed wrongly or applied in poor conditions may not cure properly.
- Primer applied to prepared concrete
- Body coat, screed or self-smoothing layer applied
- Aggregate broadcast for slip resistance where needed
- Sealer or topcoat applied
- Cure time allowed before use
Curing and return to service
Resin floors gain strength as they cure. Light foot traffic is usually possible before vehicles, and full chemical resistance takes longer still. Cure times depend on the system and the temperature. Cold buildings slow curing, so heating may be used in winter.
The contractor should give a clear programme showing when the floor can take foot traffic, light vehicles, forklifts and chemicals. Rushing a floor into service before it has cured can mark or damage the surface and shorten its life.
Protect the new floor from welding, grinding sparks and dragged equipment in the first weeks.
Line marking and handover
Once cured, safety lines, walkways and hazard zones can be marked in resin paint or embedded in the floor system. The Workplace (Health, Safety and Welfare) Regulations 1992 require traffic routes to be organised so pedestrians and vehicles can move safely, and clear floor markings support that.
At handover, the contractor should explain cleaning methods, chemicals to avoid and how to deal with minor damage. Regular cleaning with suitable products keeps a resin floor looking good and maintains slip resistance. We confirm one fixed price for the whole process after survey.
Keep a record of the system used, the date it was laid and the manufacturer's maintenance advice. If repairs are needed later, knowing exactly what is on the floor helps the contractor match it and keeps any manufacturer support valid.
Questions people also ask
How long does it take to install a resin floor?
A small epoxy coating can be laid in a day or two. Larger areas, thicker systems and phased work take longer. Preparation, repairs and cure times all affect the programme. Your contractor should give a clear timetable after surveying the floor.
Does resin flooring smell during installation?
Some resins have a noticeable odour during application, especially in enclosed areas. Ventilation reduces it. Low-odour systems are available for occupied buildings and food areas. Ask about the system's odour and ventilation needs before work starts.
Can resin be laid on old painted concrete?
Usually not directly. Old paint and coatings are removed by shot blasting, grinding or planing so the resin bonds to sound concrete. Laying over old coatings risks the whole floor failing if the original paint loses adhesion.
Written and checked by the Factory Flooring team. Read our editorial policy.
More guides
How Much Does Factory Flooring Cost in the UK?
Factory flooring in the UK costs £12–£25 per m² for a light epoxy seal, £20–£40 per m² for high-build epoxy and £35–£60 per m² for 2–4 mm…
Epoxy vs Polyurethane Factory Flooring: Which Is Best?
Epoxy flooring suits dry warehouses, workshops and light to medium manufacturing. It is hard, durable and costs £20–£60 per m² depending on…
Anti-Slip Factory Flooring: Rules, Testing and Options
UK workplace floors must not be slippery so far as reasonably practicable under the Workplace (Health, Safety and Welfare) Regulations 1992. Slip…
Food Factory Flooring Requirements in the UK
UK food factory floors must be kept in sound condition and be easy to clean and, where necessary, disinfect under food hygiene law, which usually…